New Strathearn Engineering premises near Auchterarder.
Work in progress...
7 November 2007 - Foundations in

15 November 2007 - Steel Uprights in place
24 November - Frame in place 29 November - Roofing going on

6 December - Work continues despite high winds and heavy rain.

13 December - Almost weather proof.

One month later and into the new year the exterior build is
complete and
work on the interior is well underway.
Progress continues ----->